The Roswell Report: Fact versus Fiction in the New Mexico Desert was published in 1995 by Headquarters United States Air Force. It was written in response to Representative Steven H. Schiff's request and a General Accounting Office audit, and it contains Col. Richard L. Weaver's report and 1st Lt. James McAndrew's synopsis, along with attachments, appendices and photographs. The report says researchers found no evidence of an extraterrestrial craft or crew. It concludes that the 1947 debris came from a Project MOGUL balloon train.

  • p. 3 …The importance of attachment 32, Lieutenant McAndrew's synopsis, derives from his description of Project MOGUL…
  • p. 13 …Photographs, Project MOGUL Balloon Trains 27. Table No.7, Summary of NYU Constant-Level Balloon Flights…
  • p. 14 …Crane as Project Officer for MOGUL and TORRID, June 18, 1946 9. Memo, Maj Gen Curtis…
  • p. 25 …Records were located and thoroughly explored concerning a then-Top Secret balloon project, designed to attempt…
  • p. 27 USAF in September, 1947, the USAF inherited equipment, personnel, records, policies, and procedures from the AAF…
  • p. 29 …EVOLUTION OF THE EVENT FROM 1947 TO THE PRESENT General Ramey's press conference and rancher…
  • p. 31 …This included directing searches at current offices where special or unusual projects might be carried out…
  • p. 35 …USAF records showed that between June 24, 1947, and July 28, 1947, there were five crashes…
  • p. 41 …Its name was Project MOGUL (Atch 19). Project MOGUL was a then-sensitive, classified project, whose…
  • p. 42 …These interviews confirmed that Project MOGUL was a compartmented, sensitive effort. The NYU group was responsible…
  • p. 43 …It is very probable that this Top Secret project balloon train (Flight 4), made up of…
  • p. 44 …Trakowski provided specific details on Project MOGUL and described how the security for the program was…
  • p. 45 In order to provide a more detailed discussion of the specifics of Project MOGUL and how…
  • p. 48 …Copy of Vandenberg's Appointment Book and Diary, July 7-9, 1947 16. July 9, 1947…
  • p. 51 …Schiff complaiiled then that the Defense Department had been "unresponsive" to his inquiries about the 1947…
  • p. 73 …of the physicians who participated in this project. I must respect his confidentially and anonymity. He…
  • p. 74 •Freedom of Information Act Request February 5, 1993 Paqe 3 of 3 PROJECT SIGMA The project…
  • p. 76 SUMMARY OF HQ NAIC RESEARCH INTO THE ROSWELL INCIDENT, UNIDENTIFIED FLYING SAUCERS, AND PROJECT BLUE BOOK…
  • p. 78 …study project officer from 1951-1953 and he investigated a series of reports from 1947. He…
  • p. 104 …assWted command of Ro..;\vell .~rmy Air Field on e July 1947. Colo·nel i1. H…
  • p. 106 …Headqt~':'.!"ters, this station, datod 18 July 1947. 1st Lt. Lewis c. Bohanan. former commanding o…
  • p. 108 …Officer and AACS, regarding Headquarters AMC projects. 22 July- 1947 - Dr. E. M. Townsexrl, PBS, Ft…
  • p. 183 …There was a project run by New York University, out ofHoDoman at that time. It was…
  • p. 196 …Plans .for rasearoh on Project "t.t>cuJ. 1 " z. c. lS:~.-ll, priority lA, include…
  • p. 201 …On the December 1947 baUoon project reports the "service flights" probably refer to the then Top…
  • p. 205 …GeNII was the Project Engineer for the NYU balloon project during the 1947 time frame. I…
  • p. 206 …Dr Crazy and Dr Peoples were the advance people and scientific monitors for our project Dr…
  • p. 213 …I have also been contacted by several researchers and writers and discussed project Mogul and provided…
  • p. 217 Transcript from 8 June 94, Interview with Professor Charles Moore (A) Professor Charles Moore Project Engineer…
  • p. 218 …Is there any type of material from that project that you can think of that would…
  • p. 226 …so essentially you'd say there were no radar reflectors in New Mexico until 1947 until…
  • p. 246 …We got into an operation at Alamagordo in early June of 1947, in which we were…
  • p. 261 …It turns out that during this time frame, 1947, 1948, 1949, there were numerous aircraft accidents…
  • p. 275 …I remained project officer of Project MOGUL through our move of the laboratory from Watson Laboratories…
  • p. 281 …At some point in Project MOGUL did you utilize equipment based at Roswell Army Air Field…
  • p. 299 …B-29 crashed on T/0 from Albuquerque in Jan 1947 and a B-29 crashed…
  • p. 300 …Archivist (202) 504-5416 "no records of Project Mogul; recommend checking with DOE historian or the…
  • p. 309 …However, I was familiar with them because we used them and their products on various projects…
  • p. 318 …1947.4 An examination of unclassified technical and progress reports prepared by the balloon project revealed…
  • p. 320 …in January 1947, is shown in Attachment 2. Over the course of the project, MOGUL had…
  • p. 321 Air Forces, in conjunction with Project MOGUL. 10 The NYU "balloon group" was to develop and…
  • p. 322 …June 1, 1947.19 Present Olll this flight was C.B. Moore, NYU Project Engineer, Charles…
  • p. 323 …Dr Peoples, Project Scientist, decided not to bring the radiosonde recorder (an AN IFMQ1 weighing approximately…
  • p. 326 …Over the course of Project MoGUL, several balloons had landed and been recovered from that area…
  • p. 328 …Additionally, in 1949, General Yates received a full briefing bf the projects, including constant-level balloons…
  • p. 329 …Pritchard, a Watson Laboratory Project Officer (not assigned to MOGUL) stationed at Alamogordo AAF. This article…
  • p. 330 …One instance, on April 7, 1947, Crary gave Pritchard a "progress report for MOGUL project to…
  • p. 418 …From September 1946 to Januar,r 1947, Colonel Dut!7 WRI in charge of apnlled nropagation…
  • p. 444 …was decided, during the autumn of 1947 to present the meteorological diagnoses in a different form…
  • p. 708 …20 March 1947 N. Y. Meeting No. 12 PROBLEM: 1. The Secretary of the Subcommittee presented…
  • p. 747 …1, 1947 to Ma7 31, 1947 §tqttoa II tt.aearch D1'fie ion, ProJect 1fo. 93…
  • p. 758 …January 1, 1947 to April 30, 1947 CONSTANT LEVEL BALLOON Research Division, Project No. 93 Preoared…
  • p. 776 …The project ~rsomlel !las been usiiU:; work bencl:.ea occ;.i.9ied by other projc:cts…
  • p. 790 …12. :20 l11arch 1947 PROBLEM: 1. The Secretary of t~e Subcommittee presented a request from…
  • p. 819 …June 1, 1947 to June 31, 19"7 Section II Research Division, ProJect No. 9S Prepared…
  • p. 975 …Army Air Forces, in 1947, and later Chief of Staff, United States Air Force, 1961-1965…
  • p. 979 …break during Project MOGUL operations at White Sands Proving Ground, NM, July 1947. Project MOGUL Field…
  • p. 982 …the NYU field trip in June 1947 prompted Project Engineer C.B. Moore to attach additional…
  • p. 983 …Moore, NYU Constant-Level Balloon Project Engineer. Moore pio- neered the use of polyethylene balloons for…
  • p. 984 …Sands Proving Ground, NM, in July 1947, by Project MOGUL balloon and ground-based sensors. Photo…
1947 12
in March. S on new weather calculations 20 Feb. Found adding wind directly to velocity
from temp r-i·.'es accurate enough results. Chan#!:ed 20 Feb rocket and plotted up altitudes
against signal §trength - shows nothing significant & started on 1 A~ril rocket. Have all
4 station azimuths about finished. Phil Chantz and Wiggett in by train Friday night. They
brought in records of Flights 28, 29 and JO on east coast - 1 of May and 2 in June. Went
over records Saturday and identified signals of 28 -29. Balloon expedition personnel arr-
ived Saturday evening - Peoples, Trakowski, Mears, Irelacd, Olsen, Moulton, Alden from AMS
and :roore, Schneider, Hackman, Smith, Hazzard, 2 others and a Lt Smith from Navy NYU.
29 June (Sun) NYU personnel and some of Watson Lab men working today with equipment in
north hanger. Went to Ruidoso with Mears, Trakowski, Godbee, V & E
Week of 30 June - 5 July '47 Alamogordo. Vivian worked on Tests 9 and 10, finishing all
upward data on GR3 recordings. Eileen worked on 1 April rocket, getting signal strengths
vs altitude (corrected for weather data) and started o~ime calculations to get time of
signal for correlation purposes. Appears likely that s~rength of signal is dependent on
station factors rather than anything about rocket.
Balloon tests? 7, 8, 9, and 10 off this week. Test 7, slated for 1 July postponed until
2 July as equipment was not ready. 100 tanks Helium obtained from Amarillo Monday evening.
Also radiosonde receivers set up by NYU personnel Monday but were not operable. Test 7
at dawn on July 2 with pibal 1 hr first following with th~<>dlite. Winds were very light
and balloons up between A air base and mountains most of time. Included cluster of met
balloons. Follewed by C-54? for several hours & finally landeddn mountains near road to
Cloudcroft. Before gear could be recovered, most of it had be~~tolen. Stations operating
at north hanger, Cloudcroft and ROswell. Shots made unfortunately at Site #4 and picked up
good from north hanger and from Cloudcroft for awhile. Nothing from Roswell. On Thursday
morning 3 July, a cluster of GM plastic balloons sent up for V2 recording but V2 was not
fired. No shots fired. Balloons up for some time. No recordings from Roswell as pibal showed
no W winds. Balloons picked up by radar WL and hunted by Manjak C-45. Located on Tularosa
Range qy air. Out pm with several NYU by weapon carrier but we never located it. Rocket
postponed until 730 Thursday night but at last minute before balloon went up,,V2 was called
off on account of accident at White Sands.Sent up cluster balloons with dummy load. Balloon
flight #10 at dawn on July 5th. Had gone out in C-45 again with Moser and Dubell to hunt
for balloon from Flight 8 but not since? we found them. C-54 went to El Paso and picked up
single Smith plastic balloon and GM cluster plastic balloons. Flight 10 with single
plastic followed from Alamogordo and Cloudcroft. Shot 8 shots from Site 4. Picked up most
and lost signal at 845. Balloons ? more than 6 hrs although time clock had been put in
to bring them down after 5 hrs. ? were picked up by ? C-45 as first flight out was
delayed. Had special balloon at 7 with explosice charge which went off at 35,000 ft and at
745 but by that time the receiver had lost the signal. Followed by radiosonde series until
after 1300. Cloudcroft off at 8 and doubtful about signals received.
Peoples and Trakowski up 4 July with Dr. O'Day of CFS to Alamo Tower ---- ? Solar Obser-
vatory the SCEL station. Schneider up with 0 'Day to check use as NYU station.
Alamoggrdo crew helped~.get helium, and did ground shooting of 2 July. Out July 3 at Dona
and Launching sites at 2 pm and later at night.
Finished identification on Flights 28, 29 and 30 on east coast and made plans for Bermuda
flights.
Unable to leave for home on 3 July as was planned and wired Donnie first part of week
if he could change his schedule and go home folloeing week. Got wire back that he had
decided not to make the trip.
July 6(sw&. Worked at office on flights and rocket data. Started on plans for speech 17 July
meeting NYU - Getting.ready for Flight 11. Plans are to put up Smith balloon with GM ?
plasties + simple met balloon sonobuoy + balloon bomb.
July 7 {Mon) Alamogordo. Balloon Flight 11 A off at 0503. Big plastic with small auxiliary
plastics. WL gear - radiosonde and dribbler. Followed with theodolite and receiver until
about 11. Picked up on radiosonde receiver at Roswell and followed the~.Finally came down
(at 10,000 ' cap should have punctured plastic) near Hwy 70 between Roswell and Tularosa.
Second balloon - met balloons with radio sonde up about 630. Third balloon with 2 r"/.2 #
stick TNTand caps set by pressure element to fire at 35,000' up at 0630. Surface bombing
at Site 4 from 545 to 845 at 15 min intervals. Ireland followed main receive~nly about
J/4 hr but followed radio sonde about 3 hrs. J5,000' explosion off about 655.
Vivian got all instructions for completing work on Flights 1-JO and picked all records
and filed. Sent off TWX re Bermuda Flight and wrote up memo on it. Worked with Eileen on

Cases discussed

About this file

FOIA release, from the osd collection. The PDF is mirrored here; the original link is under it. 993 pages are in the text index: search them above, or from the library's search.