SUBJECT: (U) Senator Reid Visit to 05 January 2009
(b)(3):10 USC 424:(b)(6)
02 January 2009
I. (U) PURPOSE: To provide ith the current status of the Advanced Aerospace
Weapon System Applications contract should Senator Reid raise the topic.
2. (U//FEJU □~ BACKGROUND: Senator Inouye (O-HI) and Senator Reid (D-Ncv) sponsored
language in the July 2008 Supplemental Appropriation bill for DIA to investigate foreign
advanced aerospace weapon threats from the present out to 40 years in the future. Senator Reid
has a deep interest in the potential threat posed by unconventional aerospace technologies; that
is, technologies that are a radical de arture to those used in current advanced aerospace vehicles.
In response to this tasking, the (b)(3):10 USC 424 ublished a request for
proposals (RFP) on 18 August A receive on y one 1 , rom igelow Aerospace
Advanced Space Studies (BAASS), in response to the RFP. l(b)(3):10 usc 424 !determined
that the proposal was responsive and the contract signed on 22 September 2008. Since the
Director's meeting with Senator Reid on 13 November 2008, the following items have been
completed per the contract.
3. (U) TALKING POINTS:
• (U//P@Uil) Program Management Plans. BAASS submitted the 12 technical area
program mana ement lans (PMPs) on 21 November 2008.
(b)(3):10 USC 424
==-'o~;(,;U~/~~liii~E,;;,_;;;.J;r~e~v11ie;;w;;e~,Jttthe PMPs and rated them as very good to excellent.
l(b)(3):10 usc 424 lgrante ASS approval to proceed with the technical reports.
o (U,';IF0TJ0) BAASS will deliver to DIA approximately two detailed reports per
technical area. The goal is for to have all reports by the end of July 2009.
(b)(3):10 USC 424
• (U/; POU O; Facility Clearance. The Defense Security Service conducted a site
inspection on the BAASS facility on 17 December 2008. The inspection was completed
satisfactorily and the facility clearance process is expected to be completed shortly.
• (U/'Ri?Pfa.i Contract is on track. The contract is currently proceeding on schedule and
within cost. The technical reports wilt be under subcontract by February 2009 and
completed by the end of July 2009.