Documents / Document

Apollo 11 Technical Crew Debriefing, Volume 1 (scan)

NASA via ibiblio · 1969-07-31 · 251 pages · text by OCR

This is Volume 1 of NASA's Apollo 11 Technical Crew Debriefing, dated July 31, 1969. The Mission Operations Branch of the Flight Crew Support Division at the Manned Spacecraft Center in Houston prepared it, and it was originally classified Confidential. In it Armstrong, Aldrin and Collins go phase by phase through suiting, launch, powered flight, Earth orbit and lunar surface activities. They comment on suit fit, vibration, checklists, lunar dust, footing and poor sleeping conditions in the lunar module. A section titled Visual Sightings appears in the table of contents.

  • p. 30 …It was impossible to read an effect on any indicator in the cockpit. COLLINS This is…
  • p. 38 …the expected altitude was 174 and we read 176. The EMS was 3.3 plus. ARMSTRONG…
  • p. 39 …There's no way that the EMS could read 99.1 at docking. As I recall…
  • p. 40 ## CONFIDENTIAL Then I thrusted minus X until the DELTA-V counter read minus 100.5. I…
  • p. 46 …Neil and I both read a memo put out by MPAD, saying that for some failure…
  • p. 50 …We gave daily dosimeter readings, which as far as I'm concerned fall in a sort…
  • p. 51 …COLLINS And the dosimeter we just gave them a once-a-day reading on that dosimeter…
  • p. 68 …When you read me the numbers, you didn't note that I read star number 2…
  • p. 79 …The cabin temperature (translunar) was slightly warmer than we would like it, although the gage readings…
  • p. 130 …We had good helium pressure and read that out to MSFN. We went through the RCS…
  • p. 132 …the AGS, and give you an erroneous reading so you wouldn't pass. In any case…
  • p. 134 …There is a bad amount of data that the ground reads up to you in that…
  • p. 151 …They did approach the maximum numbers with a reading of approximately 94. Anyway, they weren't…
  • p. 169 …with time as evidenced by successive LPD readings. FCOD REP. Do you recall when you proceeded…
  • p. 170 …again, although at the time we were reading relatively low tank pressures. I think the OX…
  • p. 172 …We read the sine and cosine out of AGS (and I'm sure they copied that…
  • p. 175 …we were going to launch, so we read through the remainder of the simulated countdown and…
  • p. 235 …same exercises such as pressure-integrity check, reading the cabin down, and configuring the ECS. I…
  • p. 236 …We used a sequence of marking that involved an onboard averaging of five successive cursive readings…
## CONFIDENTIAL

COLLINS I think particularly when you get into the later flights of extended EVA's and lunar activity, somehow the crew must place themselves in a frame of mind of looking on the separation of the LM as the beginning of the flight plan and to relax, get plenty of sleep, and conserve their energies in all the events leading up to that point. To arrive in lunar orbit tired can create problems and it's possible to do that if you don't approach it in the right frame of mind.

ARMSTRONG I think Mike's hit the nail on the head. We did precisely that. We got a lot of rest and got into lunar orbit eager to go to work and that's a particularly fortunate position to be in.

COLLINS This is something we've talked about before the flight and I don't know how you can get yourself in that frame of mind but I think it is a frame of mind. You have to get yourself convinced that there will be a nice relaxing couple of days going to the moon.

ALDRIN The first unusual thing that we saw I guess was 1 day out or something pretty close to the moon. It had a sizeable dimension to it, so we put the monocular on it.

## CONFIDENTIAL